Guideline to Directive 97/23/EC
1/32 District heating pipelines

Pressure equipment directive 97/23/EC

Commission’s Working Group "Pressure"

 

 

Guideline related to: Article 1, paragraphs 3.1 and 3.20

 

Question:

Are substations for district heating pipelines to be considered as “assemblies” in the Pressure Equipment Directive (PED) ?

Answer:

Yes

These substations are located after the last isolation device, normally within the con-fines of the building or industrial installation, and thus are not covered by exclusion 3.1 of Article 1.

Note:

See also guideline 3/2 when the items of the substation are joined under the responsibility of the user.

See also guideline 3/8 for the definition of an assembly.

 

Accepted by WPG on:   2002-11-05

Accepted by Working Group «pressure» on: 2003-01-27