Supported by:

Subject Area

Hydrogen and Fuel Cells

Start

MAN-Siemens-Linde PEMFC Bus Demonstration

Status
out of operation
Start date - end date 01.10.2000 - 01.04.2001
Last changes 09.08.2005
Public access
no    
Location
Germany Bavaria
Nuernberg
Erlangen, Fuerth, Nuernberg
exact location is unknown

Show Station on map
Goal
To demonstrate full cell use in puplic transportation bus under daily conditions
Description
Mobile CGH2 refueling station used in the three cities Erlangen, Fürth, Nürnberg. Filling process in two steps: 1. CGH2 overflow from trailer to bus, trailer was evacuated to 10 MPa 2. CGH2 compression to 25 Mpa Filling time: 25 min with packed Trailer 55 min with nearly evacuated Trailer Components: Trailer, Compressor (30 MPa), Dispenser, Control-Panel

Operator

Linde AG

Technology provider

Siemens

Further partners

MAN Nutzfahrzeuge

Fuel

25 MPa
Hydrogen supply
CGH2 delivery - CGH2
Hydrogen storage

CGH2 @ 20 MPa 

Vehicles served
PEMFC MAN bus
Station-contact
Station-site

Comments

MAN-Siemens-Linde PEMFC Bus Demonstration in Erlangen, Nürnberg and Fürth. Project coordination by LBST. Project received positiv feedback from passengers.
LBST-Info This Information is provided by LBST. LBST Station ID: 014
Please notice the Terms of Use. If you need more information or maps, please click here.